Production equipment scrap appraisal

Production equipment scrap appraisal-Asset Decommissioning-

Production equipment obsolescenceAppraisal Background

Production equipment refers to various mechanical equipment, electrical equipment, instrument equipment, control equipment, etc. that directly or indirectly participate in the production process. Production equipment scrapping refers to the process in which equipment has expired or is eliminated and allowed to be scrapped due to backward technology and inability to adapt to market demand. Equipment scrapping is an important link that cannot be ignored in enterprise management. It is related to many aspects such as the enterprise's economic benefits, production safety, and environmental protection.

As an independent third-party appraisal agency under Guoke Holdings, Zhongke Testing has the qualifications for fixed asset scrapping appraisal. Based on the list of assets to be scrapped and relevant information provided by the client, it can organize technical personnel to evaluate the assets to be scrapped and issue a scrapping appraisal report for production equipment.



0

Production equipment obsolescenceScrap Condition

1) The equipment has exceeded the economic life and the specified service life. Due to severe wear and tear, it has failed to meet the minimum process requirements and has no value for repair or technical transformation;

2) Although the equipment has not exceeded the specified service life, it is not qualified for use due to serious damage and has no repair value;

3) affects safety and seriously pollutes the environment. Although it can be solved by taking certain measures, it is economically uneconomical;

4) High energy-consuming equipment that is forced to be eliminated by the state;

5) Equipment that cannot continue to be used for other reasons and should not be transferred to other companies and has no retained value.

0

1

2

3

4

5

Production equipment obsolescenceAuthentication case

A batch of production equipment in a parts factory gradually entered the equipment elimination state and was parked in the warehouse for a long time. In order to determine whether the batch of equipment has reached the scrap state, our company was entrusted to appraise whether the batch of production equipment has reached the scrap state.

appraisal analysis results:

appraisal analysis expert group conducted on-site inspection and survey results on the distribution cabinet equipment entrusted for appraisal and evaluation, and made the following suggestions and conclusions :

This batch of production equipment is outdated due to its technical status and generation gap with the mainstream products in the market. It can no longer meet the current market demand. The parts are rusted and damaged, and there are no corresponding parts available on the market. It is recommended that this batch of production equipment be scrapped.


0

1

2

3

Production equipment obsolescenceAppraisal Process

1. Preliminary review; before the appraisal, it is necessary to review whether the purpose of the appraisal is reasonable and compliant, whether the appraisal conditions are met, etc., and to make a preliminary determination whether it can be done.

2. Organize materials; confirm that it can be accepted. At this time, you need to provide materials such as a list of fixed assets and reference pictures of the target. Used to calculate appraisal costs and cycles.

3, fee quotation, after receiving the materials, our agency will organize the technical department to calculate the appraisal fee, which usually takes one to two working days, and issue a formal quotation letter after calculation.

4. Sign the agreement; after the quotation letter is issued, submit it to the leaders of the relevant departments for approval. After the leaders approve, sign the technical service agreement and enter the appraisal fee payment process.

5, on-site inspection; after our agency receives the appraisal fee, we will arrange on-site inspection by technicians and experts within 1-5 working days. After the inspection, the technician will conduct investigation and analysis based on the materials and prepare a report.

06. Issue a report; the report issuance takes about 10-20 working days. After the first draft of the report is formed, it will go through the first, second, and final review, and finally the appraisal report will be issued. At this time, the number of copies of the report will be determined according to the client's needs and mailed to the client together with the invoice. If the client has any objections within 15 days after receiving the report, please reply to our agency. Our agency will organize technical staff and experts to review the appraisal report and provide a reply. If no reply is received within the time limit, our agency will assume that the relevant parties and the client recognize the relevant content in the appraisal report.